5-Day Contractor Monthly Close Standard

12-Gate Construction Month-End Close Checklist & Chart of Accounts

The 12-Gate Construction Month-End Close Checklist is a deterministic 5-day operating procedure for $2M to $50M contractors that reconciles bank statements, field-software invoices, payroll labor burden, uninstalled equipment (Account 1360), and gross ASC 606 WIP balances (Accounts 1350 and 2450) to $0.00 Trial Balance variance before financial statements go to owners, banks, or surety underwriters. Download both reference CSVs below or run your open projects directly in WIP Calculator.

Download 12-Gate Close CSVDownload 21-Account COA CSV

Part 1: The 12 Monthly Close Verification Gates

GateClose StageGL AccountsPass Condition ($0.00 Variance Rule)
GATE-011. Cash & Card Statement Lock1000-1090 / 2050Opening + Cleared Inflows - Cleared Outflows = PDF Statement Ending ($0.00 variance; zero plug JEs).
GATE-022. Bidirectional FSM Invoice Sync1200 Trade ARIssued/Paid invoices in BuildOps, ServiceTitan, Housecall Pro, or Jobber = QBO 1200 count & dollar sum.
GATE-033. Retainage Separation1210 Retainage Asset5% to 10% GC holdbacks isolated in 1210 rather than aging past 90 days inside 1200 Trade AR.
GATE-044. AR Remittance Clearing1160 Remittance Clearing1160 = $0.00 at close; zero customer bank-feed deposits posted directly to 4000 Income when open AR exists.
GATE-055. Merchant Batch Gross-to-Net1170 Processor ClearingGross FSM card/ACH closes minus net bank payouts minus 6240 fees = exact last-2-day in-transit batch.
GATE-066. Two-Leg Transfer Clearing1150 Transfer ClearingBank checking outflow debits + credit-card inflow credits to 1150 net to $0.00 without deleting bank-feed lines.
GATE-077. Consume-Once AP & Sub Bills2000 AP / 5200-5300Every vendor check/ACH linked via BillPayment to an open Bill; zero duplicate expenses or blank payees.
GATE-088. Payroll & Burden Allocation5100 / 5150 / 6150Gross payroll + taxes/WC = 5100 Job Wages + 5150 Job Burden + 6150 Unapplied Shop/Drive + 6100 Office.
GATE-099. Staged Materials & Sub Cutoff1360 / 2120 AccruedUninstalled yard chillers/switchgear held in 1360; pre-cutoff unbilled sub work accrued in 2120 (reverse Day 1).
GATE-1010. WIP-to-GL Two-Way Footing4000 & 5100-5400WIP Billed = Job 4000+1210 AND WIP Installed Cost = Job 5100-5400 with QBO Not-Specified COGS = $0.00.
GATE-1111. Prior WIP Reversal & TB Gate1350 & 2450Prior-month WIP reversed Day 1; ending TB 1350 = Gross Underbillings and TB 2450 = Gross Overbillings.
GATE-1212. Zero-Plug Provenance Sign-OffAll BS (1000-3999)Every Balance Sheet account supported by statement, subledger, or signed WIP schedule; 3000 OBE = $0.00.

Part 2: Standard Contractor QuickBooks Chart of Accounts (1150-6150)

Acct #Account NameQBO TypeWIP & Field-Software Mapping Rule
1150Inter-Account & Card Payment ClearingOther Current AssetBoth legs of bank-to-card payments route here; target ending = $0.00.
1160Unidentified Customer Receipts ClearingOther Current AssetHold unmatched wires/checks until applied via ReceivePayment to Open AR.
1170Merchant Processor Batch ClearingOther Current AssetBridges gross FSM card receipts to net bank payouts + 6240 discount fees.
1200Accounts Receivable - TradeAccounts ReceivableCollectible progress & service invoices excluding unmatured retainage.
1210Retainage ReceivableOther Current Asset5%-10% contractual holdbacks tied by job to signed Schedule of Values.
1350Costs in Excess of Billings (Underbillings)Other Current AssetGross ASC 606 WIP asset; must equal WIP Schedule Underbillings column.
1360Uninstalled Job Materials & Staged EquipmentOther Current AssetDelivered chillers/switchgear held out of WIP % complete until installed.
2110Retainage Payable (Subcontractors)Other Current Liability5%-10% withheld from subcontractors until substantial completion release.
2120Accrued Job Costs - Vendor/Sub CutoffOther Current LiabilityPre-cutoff field work whose supplier/sub invoice arrives next month.
2410Customer Deposits & Mobilization AdvancesOther Current LiabilityUpfront cash received on unstarted jobs; never book as revenue on receipt.
2450Billings in Excess of Costs (Overbillings)Other Current LiabilityGross ASC 606 WIP liability; must equal WIP Schedule Overbillings column.
2460Accrued Loss Provision on ContractsOther Current LiabilityRemaining 100% anticipated loss reserve on onerous contracts (ASC 605-35).
4000Contract & Service Revenue - BilledIncomeGross progress billings and service invoices before WIP adjustment.
4010WIP Revenue - Overbilling DeferralIncomeDebited when Billings in Excess (2450) increases during the period.
4020WIP Revenue - Underbilling AccrualIncomeCredited when Costs in Excess (1350) increases during the period.
5100Direct Field Labor - Job WagesCost of Goods SoldProductive crew wages tagged 100% to Customer:Job ($0 Not Specified).
5150Direct Field Labor - Taxes, WC & BurdenCost of Goods SoldFICA, FUTA/SUTA, trade Workers Comp class rate, and field benefits.
5200Direct Materials (Installed)Cost of Goods SoldJob-coded supply-house bills & POs excluding staged equipment in 1360.
5300Subcontractor Costs (Job-Coded)Cost of Goods SoldSubcontractor pay-apps tied to SOV, COI/W-9, and 2110 retainage.
5400Equipment Rental, Permits & RiggingCost of Goods SoldJob-specific cranes, lifts, and municipal permits.
6150Unapplied Shop, Drive & Callback LaborExpensesPaid tech hours minus job-logged hours to measure true utilization %.